Legacy 12-2024

The construction of Lancaster Legacy is progressing rapidly, with key components reaching the 38th floor – the highest level of three towers. Detailed progress of each component is as follows:

EXTERIOR FINISHING

PROGRESSING TO THE 38TH FLOOR
PROGRESSING TO THE 38TH FLOOR

PROGRESSING TO THE 38TH FLOOR

INTERIOR FINISHING

PROGRESSING TO THE 38TH FLOOR
PROGRESSING TO THE 38TH FLOOR

PROGRESSING TO THE 38TH FLOOR

FACADE INSTALLATION

PROGRESSING TO THE 38TH FLOOR
PROGRESSING TO THE 38TH FLOOR

PROGRESSING TO THE 38TH FLOOR

MEP SYSTEM INSTALLATION

ONGOING, WITH AN ANTICIPATED COMPLETION OF OVER 90%
ONGOING, WITH AN ANTICIPATED COMPLETION OF OVER 90%

ONGOING, WITH AN ANTICIPATED COMPLETION OF OVER 90%

The construction team of Lancaster Legacy is making final efforts to complete the remaining stages, ensuring the timely handover of sophisticated, high-end residences to future homeowners.